Question: 2 weeks to make Y , and 1 week to make Z . Click the icon to view the product structure and the time -

2 weeks to make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory. week 6. Additionally, a new order has been received for 90 units of S due in week 8. Modify the net material requirements plan to reflect these changes.
Construct a new net material requirements plan (enter your responses as whole numbers).
\table[[Item,,Week,\table[[Lead Time],[(weeks)]]],[,1,2,3,4,5,6,7,8],[S,Gross req,,,,,,,,,2],[On hand,,,,,,,,],[Net req,,,,,,,,],[Order receipt,,,,,,,,],[Order release,,,,,,,,],[T,Gross req,,,,,,,,,1],[On hand,,,,,,,,],[Net req,,,,,,,,],[Order receipt,,,,,,,,],[Order release,,,,,,,,],[U,Gross req,,,,,,,,,2],[On hand,,,,,,,,],[Net req,,,,,,,,],[Order receipt,,,,,,,,]]
 2 weeks to make Y, and 1 week to make Z.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!