Question: 20 marks) Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8

20 marks) Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity and find the critical path. (5 marks) b. Draw the Gantt chart using the expected duration. (5 marks) c. Calculate variance of the critical path. (5 marks) d. Calculate the probability that the project will be completed in fewer than 30 time units. (5 marks)