Question: 20. PERT/CPM chart (22points) Based on the following table, please complete the start day and finish day of for task C, D, E, G. I

20. PERT/CPM chart (22points) Based on the following table, please complete the start day and finish day of for task C, D, E, G. I and the total duration of Finish. Each answer is 2 points. TASK B D Nm TIME(DAYS) PREDECESSORS 1 2 , 3 J, F 4 CI 5 c 6 7 C,1,D 8 9 C, F, E F G H 10 Answer: Answer: Answer: 3 Answer: 4 E Answer: Answer: Answer: 5 Answer: Finish Answer: Answer: Answer: 9 -END