Question: 2.1 Construct a network diagram (with values) to analyses your project. 2.2 What is the total project duration time? 2.3 Identify the critical path on

2.1 Construct a network diagram (with values) to analyses your project. 2.2 What is the total project duration time? 2.3 Identify the critical path on your network diagram. 2.4 When is the latest time that activity G must be completed in order not to experience any delays in the project? 2.5 What is the earliest time that activity D can possibly be completed? 2.6 What is the free float for activity E with respect to activity H ? Show your calculations. 2.7 What would the implication to the project duration time be if there was a delay of 2 months in completing activity F
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
