Question: 2.2 What is the total project duration time? Answer: 2.3 Identify the critical path on your network diagram. Answer: 2.4 When is the latest time

2.2 What is the total project duration time? Answer: 2.3 Identify the critical path on your network diagram. Answer: 2.4 When is the latest time that activity G must be completed in order not to experience any delays in the project? (1) Answer: 2.5 What is the earliest time that activity D can possibly be completed? Answer: 2.6 What is the free float for activity E with respect to activity H ? Show your calculations. (4) Answer: 2.7 What would the implication to the project duration time be if there was a delay of 2 months in completing activity F ? (1) Answer: 2.2 What is the total project duration time? Answer: 2.3 Identify the critical path on your network diagram. Answer: 2.4 When is the latest time that activity G must be completed in order not to experience any delays in the project? (1) Answer: 2.5 What is the earliest time that activity D can possibly be completed? Answer: 2.6 What is the free float for activity E with respect to activity H ? Show your calculations. (4) Answer: 2.7 What would the implication to the project duration time be if there was a delay of 2 months in completing activity F ? (1)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
