Question: 2.2) Based on the diagram shown below, answer the questions: Activity Duration 2 days 6 days 7 days 3 days 4 days 4 days 14

 2.2) Based on the diagram shown below, answer the questions: Activity

2.2) Based on the diagram shown below, answer the questions: Activity Duration 2 days 6 days 7 days 3 days 4 days 4 days 14 daysha 3 days a) What is the total duration of the project? (2 marks) b What is the critical path of the project? (3 marks) C) How many days can activity A be delayed without delaying any following activities? (2 marks) d) What is the total float on activity D? (2 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!