Question: 22 The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C =

22 The network below represents a project being
22 The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, 1 = 10, and J = 6. out of E B H G Start 12 D F 10 What is the duration of the path A-B-E-H-J O a. 20 O b. 25 O c. 21 d. 30

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!