Question: 23) What is the projected Beginning on-hand on week 4 (A value) A) 100 B) 200 C) 300 D) 400 24) What is the net

23) What is the projected Beginning on-hand on week 4 (A value)
A) 100
B) 200
C) 300
D) 400
24) What is the net requirements on week 4 (B value)
A) 100
B) 400
C) 500
D) 800
25) What is the lead time for product J
A) 1 week
B) 2 weeks
C) 4 weeks
D) Cannot be determined with information provided
26) What is the planned order releases on week 1 (C value)
A) 1000
B) 400
C) 100
D) 0
27) What is the planned order releases on week 2 (D value)
A) 400
B) 300
C) 100
D) 0
28) f the lead time for component K is 1 week, what is K's gross requirement on Week 3
A) 300
B) 400
C) 600
D) Cannot be determined with the information provided
29) If each unit of product J contains 6 units of component L, the value of X on the BOM structure is:
A) 1
B) 3
C) 5
D) 6
PROBLEM 4 (10 POINTS)
On the previous problem, The Operations Manager decides to use the Economic Order Quantity Lot sizing strategy. If the EOQ is 500 units:
30) What are the net requirements on week 4 (B Value)
A) 100
B) 400
C) 500
D) 800
31) What is the planned order release on week 2 (D value)
A) 0
B) 300
C) 400
D) 500
Word File Edit View Insert Format Tools Table Window Help ALURAN 42% 1 Wed 7:00 PM Maricela Caciano QOE PROBLEM 128 POINTS The BOM structure and Material Requirements Plan for product using lot-for-lot sizing technique are shown below. K (2) LX) M(2) 1 2 Week 3 300 300 Step 81 400 Gross Requirements Beginning On hand Inventory Net Requirements Ending On hand Inventory Planned Order Receipts Planned Order Releases C D 300 23) What is the projected Beginning on-hand on week 4 (A value) A) 100 B) 200 Cj 300 D) 400 Barn Borg 10 . a DR CRIO O O ._Step by Step Solution