Question: 25 Which activity should be crashed first (2 (2 ) Activity Immediate Predecessors A B D E Normal Time Months) 6 7 7 6 9


25 Which activity should be crashed first (2 (2 ) Activity Immediate Predecessors A B D E Normal Time Months) 6 7 7 6 9 Crash Time Months) 4 5 6 4 8 Normal Cost (S) 2000 3000 1000 2000 8800 Crashing Cost (S) 2400 3500 1300 2600 9000 A B D