26 (1 point) A project manager identifies that the next following project activity resulting from a previous burst activity will possibly be delayed. What should the project manager do FIRST? Check if the activity will become a merge activity later in the project schedule network Review if sufficient resources exist to prevent delay Check if the activity is on the critical path Reschedule the entire project around this potential delay