Question: 26. When a project change is requested, what should be done first? a. Update the project schedule. b. Inform stakeholders without evaluation. c. Evaluate the
26. When a project change is requested, what should be done first? a. Update the project schedule. b. Inform stakeholders without evaluation. c. Evaluate the change's impact on the project. d. Implement the change immediately