Question: 2.A production process below is shown. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding operations. A product needs to go
2.A production process below is shown. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Sawing 6 units/hr Sanding 6 units/hr Drilling 2.4 units/hr Welding 2 units/hr Assembly 7units/hr Assembly 0.7 units/hr Asembly 0.7 units/hr a) What is the bottleneck time of the

system? b) What is the bottleneck station of this work cell? c) What is the throughput time? d) If the line operates 10 hours per day, 5 days per week, what is the weekly capacity of this work cell?