Question: 2.Given the following project information: a. Draw a node network and perform the CPM calculations of the following project. (15 points) b. Identify the critical

2.Given the following project information: a.
2.Given the following project information: a. Draw a node network and perform the CPM calculations of the following project. (15 points) b. Identify the critical path and project duration. (10 points) Activity Duration (days) Predecessors A 5 Use the following template format: B 2 A C 9 1 Activity D 4 A,B ES Duration B EF E 7 5 LS LF 10 8 3 IGH F I J NU 2 BD D D.E C,F,G C,G H,I