Question: For the project data shown below, answer the following questions: a) Draw the activity network b) Perform forward and backward path calculations c) Show the

For the project data shown below, answer the following questions:
a) Draw the activity network
b) Perform forward and backward path calculations
c) Show the critical path
For the project data shown below, answer the following questions: a) Draw the activity network b) Perform forward and backward path calculations c) Show the critical path Duration Immediate predecessor Activity A 4 IB 4 A C 8 B 3 C 15 A F 2 BE 8 C, FStep by Step Solution