Question: 2. Given the following project information: a. Draw a node network and perform the CPM calculations of the following project. (15 points) b. Identify the

2. Given the following project information: a.

2. Given the following project information: a. Draw a node network and perform the CPM calculations of the following project. (15 points) b. Identify the critical path and project duration. (10 points) Activity Duration (days) Predecessors A 5 Use the following template format: B 2 A 9 Activity D 4 A,B 7 B ES Duration EF 5 D LS LF 10 D,E C,F,G 3 C,G 2 H,I E F G H I J