Question: A project for improving a billing process has the following precedence relationships and activity times: begin{tabular}{ccc} hline Activity & Activity Time (weeks) & Immediate Predecessor(s)

A project for improving a billing process has the following precedence relationships and activity times: \begin{tabular}{ccc} \hline Activity & Activity Time (weeks) & Immediate Predecessor(s) \\ \hline A & Click \\ B & 4 & - \\ C & 10 & - \\ D & 7 & A \\ E & 14 & B, C \\ F & 9 & B \\ G & 5 & D \\ H & 3 & E \\ \hline \end{tabular} b. Calculate the slack for each activity. Which activities are on the critical path