Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) 5 Immediate Predecessor(s) a. Choose
A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) 5 Immediate Predecessor(s) a. Choose the correct network diagram below. A. S 5 ABCDEFGH 8 7 11 21430 9 A B, C B D E F, G O B. H FG S 4 9 B G 8 11 3 A F 5 4 B D 8 12 3