Question: 3 1 . An activity has an early start ( ES ) of day 3 , a late start ( LS ) of day 1

31. An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. The activity:
a) Is not on the critical path.
b) Has a lag.
c) Is processing well.
d) Is on the critical path.