Question: In the Forward and Backward passes that we do to determine the Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF)
-
In the Forward and Backward passes that we do to determine the Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF) of the activities, which one of the following statements is FALSE?
To start the backward pass, we set LF of the ending node equal to its ES
The EF of an activity is equal to the ES of this activity plus its duration
To start the forward pass, we set ES of the starting node equal to zero
The LS of an activity is equal to the LF of this activity minus its duration
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
