Question: Use the following information to answer . Calculate each activity TE (estimated duration for each activity, rounding to the nearest integer). Create a network activity
- Use the following information to answer.
- Calculate each activity TE (estimated duration for each activity, rounding to the nearest integer).
- Create a network activity diagram, its early start (ES), early finish (EF), late start (LS) and late finish (LF), and slack for each activity.
- Identify the projects critical path.
| Activity | Preceding activities | Best | Likely | Worst | TE |
| A | - | 12 | 15 | 25 |
|
| B | A | 4 | 6 | 11 |
|
| C | - | 12 | 12 | 30 |
|
| D | B, C | 8 | 15 | 20 |
|
| E | A | 7 | 12 | 15 |
|
| F | E | 9 | 9 | 42 |
|
| G | D, E | 13 | 17 | 19 |
|
| H | F | 5 | 10 | 15 |
|
| I | G | 11 | 13 | 20 |
|
| J | G, H | 2 | 3 | 6 |
|
| K | J, I | 8 | 12 | 22 |
|
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock