Question: Use the following information to answer . Calculate each activity TE (estimated duration for each activity, rounding to the nearest integer). Create a network activity

  1. Use the following information to answer.
  1. Calculate each activity TE (estimated duration for each activity, rounding to the nearest integer).
  2. Create a network activity diagram, its early start (ES), early finish (EF), late start (LS) and late finish (LF), and slack for each activity.
  3. Identify the projects critical path.

Activity

Preceding activities

Best

Likely

Worst

TE

A

-

12

15

25

B

A

4

6

11

C

-

12

12

30

D

B, C

8

15

20

E

A

7

12

15

F

E

9

9

42

G

D, E

13

17

19

H

F

5

10

15

I

G

11

13

20

J

G, H

2

3

6

K

J, I

8

12

22

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!