Question: 3 . ( 2 0 % ) You must schedule a project with activities below. Assume the latest finish time is equal to the earliest

3.(20%) You must schedule a project with activities below. Assume the latest finish time is equal to the earliest finish time.
Activity Predecessors Duration (days)
A -3
B A 4
C A 6
D B 3
E B 2
F E 3
G C, D 2
H G 4
I H 4
a. Construct an Activity on Node representation of the project and perform the forward and backward passes to determine earliest and latest start and finish times.
b. State the activities along the critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!