Question: 3 . ( 2 0 % ) You must schedule a project with activities below. Assume the latest finish time is equal to the earliest
You must schedule a project with activities below. Assume the latest finish time is equal to the earliest finish time.
Activity Predecessors Duration days
A
B A
C A
D B
E B
F E
G C D
H G
I H
a Construct an Activity on Node representation of the project and perform the forward and backward passes to determine earliest and latest start and finish times.
b State the activities along the critical path.