Question: 3. (20%) You must schedule a project with activities below. Assume the latest finish time is equal to the earliest finish time. Activity Predecessors
3. (20%) You must schedule a project with activities below. Assume the latest finish time is equal to the earliest finish time. Activity Predecessors Duration (days) AABBE ABCDEFGHI C, D G H 3 3 2 2 a. Construct an Activity on Node representation of the project and perform the forward and backward passes to determine earliest and latest start and finish times. b. State the activities along the critical path.