Question: 3 . 2 For a data migration project ( Mega IT project ) at a large company of which you are the project manager, you
For a data migration project Mega IT project at a large company of which you are the project manager, you must control the costs of the project. Phase will take six months to complete, and you are three months into it The partial structure of Phase is as follows:
For A and which are subaccounts of the Phase account, you have the following information:
tabletableProjectSubAccountBCAC,ACWP,BQAC,AQWP,tablePercentagecompleteBCWSAB
Calculate the following values, rounding to two decimals:
a Cost variance CV
A:
B:
b Schedule variance SV
A:
B:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
