Question: 3 . 2 For a data migration project ( Mega IT project ) at a large company of which you are the project manager, you

3.2 For a data migration project (Mega IT project) at a large company of which you are the project manager, you must control the costs of the project. Phase 1 will take six (6) months to complete, and you are three (3) months into it. The partial structure of Phase 1 is as follows:
(11)
For A and B, which are sub-accounts of the Phase 1 account, you have the following information:
\table[[\table[[Project],[Sub-],[Account]],BCAC,ACWP,BQAC,AQWP,\table[[Percentage],[complete],[(%)]],BCWS],[A,110,00,77,00,250,00,21,00,51%,54,00],[B,117,00,67,00,321,00,112,00,39%,43,00]]
C. Schedule performance index (SPI)(2)
A: ,SPI =?
B: ,SPI =?
d. Cost performance index (CPI)(2)
A: ,CPI =?
B: ,CPI =?
e. Forecasted cost at completion (FCAC) for each account (Method 1)
(3)
A: , FCAC =?
B: ,FCAC=?
Total: Method 1 total FCAC of Phase 1=?
 3.2 For a data migration project (Mega IT project) at a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!