Question: 3 . 2 For a data migration project ( Mega IT project ) at a large company of which you are the project manager, you
For a data migration project Mega IT project at a large company of which you are the project manager, you must control the costs of the project. Phase will take six months to complete, and you are three months into it The partial structure of Phase is as follows:
For A and which are subaccounts of the Phase account, you have the following information:
tabletableProjectSubAccountBCAC,ACWP,BQAC,AQWP,tablePercentagecompleteBCWSAB
C Schedule performance index SPI
A: I
B: I
d Cost performance index CPI
A: I
B: I
e Forecasted cost at completion FCAC for each account Method
A: FCAC
B: FCAC
Total: Method total FCAC of Phase