Question: 3 . 2 In a batch machining operation, setup time is 1 . 5 h r and batch size is time consists of part handling
In a batch machining operation, setup time is and batch size is time consists of part handling time of and processing time of min. One part is produced each cycle. Tool changes must be performed every parts and this takes min. Determine a average cycle time, b time to complete the batch, and c average production rate.
A batch production operation has a machine setup time of and a processing time of
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock