Question: In a batch machining operation, setup time is 1.5 hours and batch size is 80 units. The cycle time consists of part handling time of

In a batch machining operation, setup time is 1.5 hours and batch size is 80 units. The cycle time consists of part handling time of 30 sec and processing time of 1.37 min. One part is produced each cycle. Tool changes must be performed every 10 parts and this takes 2.0 min. Determine (a) average cycle time, (b) time to complete the batch, and (c) average production rate. Fill in the blanks (Please round to two decimal points ): A. The average cycle time is 0.21 minutes . B. The time to complete the batch is hours. C. The average production rate is pieces per hour.