Question: In a batch machining operation, setup time is 1.25 hours and batch size is 90 units. The cycle time consists of part handling time of

In a batch machining operation, setup time is

In a batch machining operation, setup time is 1.25 hours and batch size is 90 units. The cycle time consists of part handling time of 45 sec and processing time of 1.5 min. One part is produced each cycle. Tool changes must be performed every 12 parts, and this takes 2.5 min. Determine (a) average cycle time, (b) time to complete the batch, and (c) average production rate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!