Question: 3 - 2 Question 1 , Problem $ 7 . 9 HW Score: 0 % , 0 of 1 8 pointsO Points: 0 of 2

3-2Question 1, Problem $7.9HW Score: 0%,0 of 18 pointsO Points: 0 of 2@SaveA production line at V. J. Sugumaran's machine shop has three stations. The first station can process a unit in 5 minutes. The second station has three identical machines, each of which can process a unit in 18 minutes (each unit only needs to be processed on one of the three machines). The third station can process a unit in 7 minutesY is the bottleneck station, with a bottleneck time of minutes per unit (enter your response as a whole number).