Question: 3 . 3 9 Calculate the expected time for the following activities. table [ [ Activity , Optimistic Time,Most Likely Time,Pessimistic Time,Expected Time ]

3.39 Calculate the expected time for the following activities.
\table[[Activity,Optimistic Time,Most Likely Time,Pessimistic Time,Expected Time],[A,3,7,11,],[B,5,9,13,],[C,1,2,9,],[D,2,3,16,],[E,2,4,18,],[F,3,4,11,],[G,1,4,7,],[H,3,4,5,],[1,2,4,12,],[J,4,7,9,]]
 3.39 Calculate the expected time for the following activities. \table[[Activity,Optimistic Time,Most