Question: 3 6 Class Activity Develop AON network for the following project: table [ [ Activity # , Predecessors,Dur. ( day ) , Lag (

36
Class Activity
Develop AON network for the following project:
\table[[Activity #,Predecessors,Dur. (day),Lag (day)],[A,--,1,0],[B,A,2,SS,2],[C,A,3,FS,2],[D,B,4,FF,1],[E,C,5,FS,3],[F,D and E,6,D: FS,5],[,,,E: FF,3]]