Question: Develop AON network for the following project: Predecessors Activity # Dur. (day) Lag (day) A B C A A 2 3 4 5 D oo

Develop AON network for the following project:
Develop AON network for the following project: Predecessors Activity # Dur. (day) Lag (day) A B C A A 2 3 4 5 D oo AN B C D and E 0 SS,2 FS, 2 FF,1 FS,3 D: FS,5 E: FF,3 37 E F 6