Question: 3 8 . ( 2 0 points ) FlexSteal, marketed as a miracle brush - on sealant and baldness cure, is manufactured at three plants

38.(20 points) FlexSteal, marketed as a miracle brush-on sealant and baldness cure, is
manufactured at three plants that are struggling to keep up with the demand at the
four regional centers. The cost to ship a truckload from each of the existing plants to
the regional centers is shown in the table. Note that the capacity and the total demand
are both measured in truckloads.
Philadelphia Atlanta Dallas Los Angeles Capacity
Plant 1897593115400
Plant 21208810393400
Plant 3958211298400
Total Demand 350350350350
The supply chain manager has explored plant construction costs in two other cities as
well as the cost to ship a truckload from each of the plants to the regional centers. The
current plan is to build another plant with a capacity of 400 to allow room for sales
growth. The construction cost for the new plants and cost to ship to each of the
regional centers is shown here.
Philadelphia Atlanta Dallas Los Angeles Cost to Build
Plant A 94789595 $23,500
Plant B 95888894 $26,000
(a)(5 points) What is the lowest cost solution for the existing set of plants and
regional centers?
(b)(5 points) Setup objective function.
(c)(10 points) Setup constraints.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!