Question: . . 3 . 8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities

..3.8
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR(S),TIME (DAYS)],[A,-,2],[B,-,5],[D,B,1],[E,A, D,10],[G,C, F,8]]
a. What is the project length?
b. What are the critical activities?
c. How much slack is in activity C.?
d. What is the early start/early finish and the late start/late finish for activity F.?
e. What if activity F was delayed by 12 days. What impact would it have on the project and critical path?
 ..3.8 Roger Ginde is developing a program in supply chain management

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!