Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | 4 | |
| B | 6 | |
| C | 3 | |
| D | B | 10 |
| E | A, D | 5 |
| F | C | 6 |
| G | E, F | 12 |
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
c) Calculate slack time for all activities (show work please, meaning earliest/latest start/finish)
.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts