Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activity

Immediate Predecessor(s)

Time (days)

A

4

B

6

C

3

D

B

10

E

A, D

5

F

C

6

G

E, F

12

This exercise contains only parts b, c, and d.

b) The critical activities for the leadership training program development project are

c) Calculate slack time for all activities (show work please, meaning earliest/latest start/finish)Roger Ginde is developing a program in supply

.Roger Ginde is developing a program in supply

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed conducted. The activities, immediate predecessors, and times appear in the accompanying table: number of activities that must be completed before a training program of this nature could be Immediate Predecessor(s) Activity B Time (days) 4 6 3 10 D E F B AD EF 5 6 12 G This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G D C-F-G A-E-G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!