Question: 3 8 Use the S - curve where the solid line is actual cost and the dashed line is budgeted cost to choose the BEST

38 Use the S - curve where the solid line is actual cost and the dashed line is budgeted cost to choose the BEST state Actual Budget $ 140,000 $ 130,000 $ 120,000 $ 110,000 $ 100,000 $ 90,000 $ 80,000 $ 70,000 $ 60,000 $ 50,000 $ 40,000 $ 30,000 $ 20,000 $ 10,000 $ 0481216202428323640 elect one : . The project is further ahead of budget from weeks 36 through 40 than from weeks 8 through 12 B. The project never experiences negative variance . C. The project is in a constant state of positive variance . The project is further behind budget from weeks 0 through 16 than from 24 through 40.