Question: Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the BEST statement. Select one: A.

 Use the S-curve where the solid line is actual cost and

Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the BEST statement. Select one: A. The project never experiences negative variance. B. The project is further behind budget from weeks 0 through 16 than from 24 through 40 . C. The project is further ahead of budget from weeks 36 through 40 than from weeks 8 through 12 . D. The project is in a constant state of positive variance