Question: 3 8 Which tool would a project team use to establish precedence relationships for the activity list of each work package identified in the work

38 Which tool would a project team use to establish precedence relationships for the activity list of each work package identified in the work breakdown structure (MBS)?
Resource breakdown structure (RBS)
Project statement of work (SOW)
Nelwork diagram
Gantl chart
 38 Which tool would a project team use to establish precedence