Question: 3. (a) Control chart is a graphical presentation of process data over time. Explain the purpose of the following control charts, with one example for
| 3. | (a) | Control chart is a graphical presentation of process data over time. Explain the purpose of the following control charts, with one example for each chart. i) Mean chart ii) Range chart iii) p-chart iv) c-chart |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
| (b) | Assignable variation is defined as variation in a production process that ca be traced to specific causes. List two possible causes of assignable variation. |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
| (c) | The time needed for checking in at a hotel is to be investigated. Historically, the process has had a standard deviation equal to 0.146. The means of 26 samples of n=14 are shown below.
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||