Question: 3. (a) Draw a network diagram given the following information: Activity Nodes Duration J 1-2 10 1-3 8 2-4 6 2-3 3 N 3-4 2

3. (a) Draw a network diagram given the following
3. (a) Draw a network diagram given the following information: Activity Nodes Duration J 1-2 10 1-3 8 2-4 6 2-3 3 N 3-4 2 0 4-5 7 P 3-5 (b) A project has been defined for the network and their required times (days) for completion below. Start 2 Calculate the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF) and slack. Show the critical path. K L M

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!