Question: 3. A network diagram is provided using the Activity on Arrow (AOA) format. Find ES, EF, LS, LF, and slack values all activities. Activities a

3. A network diagram is provided using the Activity on Arrow (AOA) format.

Find ES, EF, LS, LF, and slack values all activities. Activities a and b start on day 0.

Immediate Duration

Activity Predecessors (days)

a. organize layout team - 2

b. organize modification team - 3

c. design personnel jobs a 3

d. set machinery in place b 4

e. connect utilities c,d 4

f. modify conveyor system e 4

g. train personnel e 5

h. finishing touches f 4

i. run test lot g 3