Question: 3. A network diagram is provided using the Activity on Arrow (AOA) format. Find ES, EF, LS, LF, and slack values all activities. Activities a
3. A network diagram is provided using the Activity on Arrow (AOA) format.
Find ES, EF, LS, LF, and slack values all activities. Activities a and b start on day 0.
Immediate Duration
Activity Predecessors (days)
a. organize layout team - 2
b. organize modification team - 3
c. design personnel jobs a 3
d. set machinery in place b 4
e. connect utilities c,d 4
f. modify conveyor system e 4
g. train personnel e 5
h. finishing touches f 4
i. run test lot g 3
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts