Question: 3. A network diagram is provided using the Activity on Arrow (AOA) format. Find ES, EF, LS, LF, and slack values all activities. What is

3. A network diagram is provided using the

3. A network diagram is provided using the Activity on Arrow (AOA) format. Find ES, EF, LS, LF, and slack values all activities. What is the critical path(s)? Activities A and B start on day o. a Immediate Duration Activity Predecessors (days) a. organize layout team 3 b. organize modification team- 6 c. design personnel jobs 6 d. set machinery in place e. connect utilities sed 7 f. modify conveyor system 4 g. train personnel 5 h. finishing touches f 4 run test lot 3 e e