Question: 3. A network diagram is provided using the Activity on Arrow (AOA) format. Find ES, EF, LS, LF, and slack values all activities. What is

3. A network diagram is provided using the Activity on Arrow (AOA) format. Find ES, EF, LS, LF, and slack values all activities. What is the critical path(s)? Activities A and B start on day 0. Immediate Duration Activity Predecessors (days) a. organize layout team 3 b. organize modification team- 6 c. design personnel jobs a 6 d. set machinery in place b 4 e. connect utilities cd 7 f. modify conveyor system e 4 g. train personnel e 5 h. finishing touches f 4 i. run test lot g 3 ON LN ga 2 a a h e 5 8 b d 3