3. A project networkis shown below. Use a forward anda backward pass to determine the critical path and then fill out the table below. G 3 D 4 Finish Start B H 0 E 12 8 F 10 Activity Time (weeks) Critical Path? ES LS EF LF Precedence Activity Activities A B Slack D E F G H I Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in more than 28 weeks more or less than 50%