Question: 3. Construct a project network for the following project. The project is completed when activities F and G are both complete. Activity A BCDE F

3. Construct a project network for the following project. The project is completed when activities F and G are both complete. Activity A BCDE F G Immediate Predecessor A A C,B C,B D, E