Construct a project network for the following project. The project is completed when activities F and G are both complete.
| Activity | A | B | C | D | E | F | G |
|---|---|---|---|---|---|---|---|
| Immediate Predecessor | - | - | A | A | C, B | C, B | D, E |
A project network is given with the starting point on the left and the finish point on the right with activities A through G. The arcs between the activities are listed as follows.
- Start to A and B
- A to C and D
- B to C and F
- C to E
- D to G
- E to G
- F to Finish
- G to Finish
A project network is given with the starting point on the left and the finish point on the right with activities A through G. The arcs between the activities are listed as follows.
- Start to A and B
- A to C and D
- B to C and F
- C to E and F
- D to G
- E to G
- F to Finish
- G to Finish
A project network is given with the starting point on the left and the finish point on the right with activities A through G. The arcs between the activities are listed as follows.
- Start to A and B
- A to C and D
- B to E and F
- C to E and F
- D to G
- E to G
- F to Finish
- G to Finish
A project network is given with the starting point on the left and the finish point on the right with activities A through G. The arcs between the activities are listed as follows.
- Start to A and B
- A to D and E
- B to C and F
- C to E and F
- D to G
- E to G
- F to Finish
- G to Finish