Question: 3. Construct an activity-on-arrow precedence diagram. Determine the different paths, the expected path durations and the critical path. Activity Preceding Activity Time (weeks) Activity T

3. Construct an activity-on-arrow precedence

3. Construct an activity-on-arrow precedence diagram. Determine the different paths, the expected path durations and the critical path. Activity Preceding Activity Time (weeks) Activity T Time (vvecks) Preceding Activity B CE 4 7 : D F G 3 4. Construct an activity-on-arrow precedence diagram. Preceding Activity Activity Activity A Preceding Activity A, D F C G E,F