Question: 3. Construct an activity-on-arrow precedence diagram. Determine the different paths, the expected path durations and the critical path. Activity Preceding Time Activity Preceding Time Activity

3. Construct an activity-on-arrow precedence
3. Construct an activity-on-arrow precedence diagram. Determine the different paths, the expected path durations and the critical path. Activity Preceding Time Activity Preceding Time Activity (weeks) Activity (weeks) A 1 E B 2 B F C.E 7 A 1 G D D B H F.G 3 4 2 4. Construct an activity-on-arrow precedence diagram. Activity Preceding Activity Preceding Activity Activity A A.D B E.F D E F G B