Question: Dummy PERT problem 1 Draw the network and identify the critical path for the following project. Please calculate the earliest-latest start and finishing times for
Dummy PERT problem 1
Draw the network and identify the critical path for the following project. Please calculate the earliest-latest start and finishing times for each activity. Please show the expected time for 68%, 90% and 95% confidence limit for the project:
Activity Preceding Activity Time (weeks) Optimistic Time. Pessimistic time
A ___ 4 2 6
B ___ 6 5 7
C A, B 7 5 9
D B 8 7 9
E B 5 2 8
F C 5 1 9
G D 7 6 8
H D, E 8 6 10
I F, G, H 4 3 5
Please note
- A and B Activities originate from the Start Node
- C needs both A and B to start, but they are at different times
- A Dummy activity has 0 time, ES=EF match end of preceding activity, LS = LF match the beginning of following activity
- Activity H needs both D and E to finish before starting
- Activity I is the end activity with the 3 input activities: F G & H