Question: Dummy PERT problem 1 Draw the network and identify the critical path for the following project. Please calculate the earliest-latest start and finishing times for

Dummy PERT problem 1

Draw the network and identify the critical path for the following project. Please calculate the earliest-latest start and finishing times for each activity. Please show the expected time for 68%, 90% and 95% confidence limit for the project:

Activity Preceding Activity Time (weeks) Optimistic Time. Pessimistic time

A ___ 4 2 6

B ___ 6 5 7

C A, B 7 5 9

D B 8 7 9

E B 5 2 8

F C 5 1 9

G D 7 6 8

H D, E 8 6 10

I F, G, H 4 3 5

Please note

  1. A and B Activities originate from the Start Node
  2. C needs both A and B to start, but they are at different times
  3. A Dummy activity has 0 time, ES=EF match end of preceding activity, LS = LF match the beginning of following activity
  4. Activity H needs both D and E to finish before starting
  5. Activity I is the end activity with the 3 input activities: F G & H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!