Question: 3) Determine the net present value for a project that costs $250,000 and is expected to yield cash flows of 30,000 per year for the

3) Determine the net present value for a project that costs $250,000 and is expected to yield cash flows of 30,000 per year for the first ten years, $35,000 per year for the following ten years, and $50,000 per year for the remaining ten years. Assume that the discount rate) is 12.00% UPV (12%, 10): 5.650, SPV (12%, 10): 0.322, SPV (12%, 20): 0.104